Midland Expressway Ltd v Carillion Construction Ltd & Others
The case of Midland Expressway Ltd. v Carillion Construction Ltd., Alfred MacAlpine Construction Ltd., Balfour Beatty Group Ltd., AMEC Capital Projects Ltd., John E. Price (No.2) [2005] concerned the new M6 toll road construction near Birmingham and is important with regard to Private Finance Initiatives (PFIs) and Public Private Partnerships (PPPs).
The four defendant contractors worked together as a joint venture called CAMBBA. A concession agreement was granted in 1992 by the Secretary of State to Midland Expressway Ltd. (MEL) for them to design, construct and operate the M6 Toll Road. MEL and CAMBBA entered into a design and construct sub-contract in 2000.
‘Equivalent project relief’ provisions were contained within the sub-contract which limited the sub-contractor’s (CAMBBA) right to payment for variations and delay to the amount that MEL was able to recover from the Secretary of State. A mechanism that was intended to ensure this in the sub-contract restricted the subcontractor’s right to adjudicate an issue until a relevant adjudication had been brought between MEL and the Secretary of State.
As a result of variations, CAMBBA made claims for additional payment which, when they were disputed, CAMBBA wished to refer to adjudication. In response, MEL applied for a declaration and injunction preventing them from referring the claim to adjudication, arguing that the sub-contract did not provide them with any jurisdiction. The correct dispute, according to MEL, was between the Secretary of State and CAMBBA, as they were only a conduit between them.
CAMBBA argued that the ‘equivalent project relief’ and adjudication provisions in the subcontract cut across the statutory entitlement under the Housing Grants, Construction and Regeneration Act (HGCRA). Section 108 states that a subcontractor is entitled to commence an adjudication ‘at any time’. As the design and construct contract was a legitimate ‘contract’ under HGCRA, the dispute could be referred to adjudication.
The Technology and Construction Court (TCC) agreed with CAMBBA, and it was held that the adjudication provisions in the sub-contract were invalid. The ‘pay when paid’ aspect of the ‘equivalent project relief’ provisions was viewed as infringing section 113 of HGCRA which sought to guard against such clauses. Therefore, CAMBBA did not have to wait to be able to refer the dispute to adjudication.
Since previously, ‘equivalent project relief’ provisions had ensured that contractors were able to act as conduits for subcontractor claims without having liability, the repercussions of the case were that limiting the right to adjudication could no longer be used as a mechanism for meeting that objective.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.